日调节性能水电站节水增发电量考核方法研究

武世峰

分布式能源 ›› 2019, Vol. 4 ›› Issue (1) : 22-26.

PDF(777 KB)
PDF(777 KB)
分布式能源 ›› 2019, Vol. 4 ›› Issue (1) : 22-26. DOI: 10.16513/j.cnki.10-1427/tk.2019.01.005
学术研究

日调节性能水电站节水增发电量考核方法研究

作者信息 +

Assessment Method of Water-Saving and Power-Increasing Capacity of Hydropower Station's Daily Regulating Performance

Author information +
文章历史 +

摘要

通过对汉江上游流域不同调节性能水电站节水增发电量考核现状的分析,提出相对发电耗水率和水能利用提高率两个考核指标的概念,定义日调节性能水电站节水增发电量计算有关参数,制定节水增发电量计算流程;通过在汉江喜河水电站的实践应用对该研究进行数据分析验证,结果表明:基于日调节性能的水电站节水增发电量考核方法合理可行。

Abstract

This paper analyses the assessment current situation of the hydropower station water-saving and power-increasing capacity with different regulating performance in the Hanjiang river upstream basin, puts forward two concepts of assessment index: water consumption for power generation and water energy utilization rate, defines the relevant calculating parameters of water-saving and power-increasing capacity of daily regulating performance of hydropower station, and establishes the water power calculation process of water-saving and power-increasing capacity. Data analysis and validation of the study are carried out through practical application of Xihe Hydropower Station on Hanjiang River. The results show that the assessment method of water-saving and power-increasing capacity of hydropower station based on the daily regulation performance is reasonable and feasible.

关键词

水电站 / 日调节 / 增发电量 / 考核

Key words

hydropower station / daily regulation / power-increasing capacity / assessment

引用本文

导出引用
武世峰. 日调节性能水电站节水增发电量考核方法研究[J]. 分布式能源. 2019, 4(1): 22-26 https://doi.org/10.16513/j.cnki.10-1427/tk.2019.01.005
Shifeng WU. Assessment Method of Water-Saving and Power-Increasing Capacity of Hydropower Station's Daily Regulating Performance[J]. Distributed Energy Resources. 2019, 4(1): 22-26 https://doi.org/10.16513/j.cnki.10-1427/tk.2019.01.005

参考文献

[1]
吴东平. 水电站运行参数和考核指标的改进建议[J]. 水力发电2001(2): 46-47, 53.
[2]
LIU Zhao, HUANG Qiang, YAN Ailing, et al. Research on the assessment system for water economization and power generating improvement of Gongboxia power station[J]. Journal of Xi'an University of Technology, 2006, 22(4): 399-402.
刘招,黄强,燕爱玲,等. 公伯峡水电站节水增发考核方法研究[J]. 西安理工大学学报2006, 22(4): 399-402.
[3]
CHANG Jianxia, WANG Yimin, HUANG Tinglin, et al. Examining computation study of economic operation of hydropower station[J]. Journal of Hydroelectric Engineering, 2006, 25(5):1-4, 30.
畅建霞,王义民,黄廷林,等. 水电站经济调度考核计算研究[J]. 水力发电学报2006, 25(5): 1-4, 30.
[4]
周建峰. 关于水能利用提高率计算办法的讨论[J]. 云南水力发电1994, 37(4): 63-65.
[5]
JIN Shaobo, SHEN Yanqing. Study on assement indicators for economic operation of hydropower station[J]. Northwest Hydropwer, 2014(3): 105-107.
靳少波,沈延青. 水电站经济运行考核指标改进研究[J]. 西北水电2014(3): 105-107.
[6]
BAI Xiaoyong, RAN Benyin, LI Guanghui. Evaluation of water saving and power generation increase of the cascade hydropower stations on the upper Yellow River[J]. Hydropower Automation and Dan Monitoring, 2007, 31(1): 25-31.
白小勇,冉本银,李广辉. 黄河上游梯级水电站群节水增发电考核[J]. 水电自动化与大坝监测2007, 31(1): 25-31.
[7]
CAI Jianzhang, CAI Huaxiang, WU Jingping. Calculation method for hydropower stations abandoning energy[J]. Automation of Electric Power Systems, 2000, 24(10): 64-65.
蔡建章,蔡华祥,吴京平. 水电站弃水电量计算探讨[J]. 电力系统自动化2000, 24(10): 64-65.
[8]
XUE Jinhuai. Research on value of K in hydropower calculation[J]. Advances of Power System & Hydroelectric Engineering, 2008, 24(3): 27-29.
薛金淮,关于水能计算中K值的探讨[J]. 电网与水力发电进展2008, 24(3): 27-29.
[9]
景连才,关于日调节水电站水能设计中的几个问题[J]. 东北水利水电1986(8): 11-14.
[10]
孙德锁,刘永前,史健. 水电站节水增发电考核方法研究[J]. 中国电力教育2007(): 189-191.
S2
[11]
国家电力公司北京勘测设计研究院,北京国电水利电力工程有限公司. 陕西汉江喜河水电站可行性研究报告(等同设计)第四篇动能部分[R]. 北京:国家电力公司北京勘测设计研究院,北京国电水利电力工程有限公司,2001.

编委: 谷子
PDF(777 KB)

Accesses

Citation

Detail

段落导航
相关文章

/