风电项目精细化开发技术要点
李斌
辽宁大唐国际新能源有限公司,辽宁 沈阳 110116
Key Points of Fine Development Technology for Wind Power Projects
LI Bin
Liaoning Datang International Renewable Power Ltd., Co., Shenyang 110116, Liaoning Province, China
全文: PDF(11158 KB)   HTML
输出: BibTeX | EndNote (RIS)      
摘要: 

当前,我国风电发展迅猛,已成为全球最大风电产业发展基地,风电项目前期开发却面临着政策更迭、补贴退坡、用地限制等多重制约因素影响,核准周期长、工程基建慢、产能收益低、政策变化快等问题日益凸显。为破解风电前期项目开发“瓶颈难题”,该文深入分析前期风电项目开发建设的各项难点因素,通过深入排查核准过程中的各项边界条件,加强实时政策研究和科学选址论证,促进各项前期专题要件并行推进,透视前期风电项目发展现状,分析开发建设严峻形势,阐明精细化开发的作用及意义,助力前期项目高质量推进。

关键词: 策略提高效益精细化前期核准开发全生命周期    
Abstract

At present, China's wind power industry is developing rapidly and has become the largest wind power industry development base in the world. However, the pre-development of wind power projects is facing multiple constraints such as policy change, subsidy recession, land restriction and so on. The serious problems such as long approval cycle, slow construction of project infrastructure, low yield and rapid policy change are becoming increasingly prominent. In order to solve the ‘bottleneck problem’ in the development of wind power projects in the early stage, this paper thoroughly analyses the various difficult factors in the development and construction of wind power projects in the early stage. Through thorough investigation and approval of the various boundary conditions in the process, real-time policy research and scientific site selection demonstration are strengthened to promote the parallel advancement of various pre-project thematic elements. This paper implements the perspective of the development status of wind power projects in the early stage, analyzes the severe situation of development and construction, clarifies the role and significance of fine development, and helps to promote the high quality of pre-project.

Key Wordsstrategyimprovementbenefitrefinementpreliminaryapprovaldevelopmentlife cycle
收稿日期: 2019-03-27

引用本文:

李斌. 风电项目精细化开发技术要点[J]. 分布式能源, 2019, 4(4): 62-67.
LI Bin. Key Points of Fine Development Technology for Wind Power Projects[J]. Distributed Energy, 2019, 4(4): 62-67.

链接本文:

http://der.tsinghuajournals.com/CN/10.16513/j.cnki.10-1427/tk.2019.04.010      或      http://der.tsinghuajournals.com/CN/Y2019/V4/I4/62

表1  “十二五”以来风电项目梳理类型及处理措施
图1  某风电场选址林业限制开发区核对图
图2  某风电场选址机位基本农田核实图
图3  某风电场选址机位压矿避让图
图4  某风电场机位、道路、集电线路规划图
[1] 秦海岩. 现阶段我国风电行业面临的主要问题综述[J]. 风能,2012 (12)58-61.
[2] 蔡晓峰,高伟,刘欣. 论风电开发的可持续发展[J]. 科研,2016, 11 (11): 275-275.
[3] 李文清,钟成. 风电开发中存在问题的探讨[J]. 浙江电力,2010, 29(1): 51-53.
[4] 孙唯宓. 浅析风力发电前期开发的流程管控构架[J]. 丝路视野,2017, 5 (31): 143-143.
[5] ZHOU Benxi. Analyze the investment risk and countermeasure of wind power development enterprise[J]. Telecom Power Technologies, 2018, 36 (4): 233-234.
[5] 周本希. 风电开发企业投资风险与对策[J]. 通信电源技术,2018, 36 (4): 233-234.
[6] WANG Xiping, LI Chongye. Research on investment decision of wind power project under carbon trading scheme[J]. Electric Power Science and Engineering, 2018, 34(7): 25-31.
[6] 王喜平,李崇烨. 碳交易机制下风电项目投资决策研究[J]. 电力科学与工程,2018, 34(7): 25-31.
[7] 杨岳涛. 中国风电开发政策现状及发展前景[J]. 山西煤炭管理干部学院学报,2014, 32(3): 69-71.
[8] 任跃攀,申琳. 审批权下放后风电项目开发建议[J]. 中国电力企业管理,2017, 37 (1): 46-47.
[9] LI Bin, ZHANG Haichao, BAI Xuefeng. Research and application of large data technology to enhance power generation of wind farm[J]. Distributed Energy, 2017, 2 (4): 23-29.
[9] 李斌,张海超,白雪峰. 大型风电场测风数据全生命周期的探讨[J]. 分布式能源,2017, 2 (4): 23-29.
[10] LI Bin, ZHANG Yushi. Research and application of low wind speed wind farm resource development[J]. Distributed Energy, 2017, 2 (2): 44-50.
[10] 李斌,张宇时. 低风速风电场资源开发的探讨及应用[J]. 分布式能源,2017, 2 (2): 44-50.
[11] ZENG Jie, CHEN Xiaoke. Short-term wind power prediction algorithm considering missing wind measurement data[J]. Renewable Energy, 2017, 2(35): 298-303.
[11] 曾杰,陈晓科. 考虑测风数据缺失的短期风电功率预测算法[J]. 可再生能源,2017, 2(35): 298-303.
[12] LI Bin, HOU Yingjun. Technical support and practical application for the development of low wind speed wind farm[J]. Northeast Electric Power Technology, 2017, 40 (7): 22-24.
[12] 李斌,侯英俊. 低风速风电场开发的技术支持及实际应用[J]. 东北电力技术,2017, 40 (7): 22-24.
[13] LIU Suyun, WANG Di, JIANG Dan. Scenario probability-based siting and sizing of wind turbine generators[J]. Electrical Automation, 2014, 36 (5): 38-40.
[13] 刘苏云,王笛,蒋丹. 基于场景概率的风电机组的选址和定容[J]. 电气自动化,2014, 36 (5): 38-40.
[14] ZHONG Wei, GE Ying, ZHANG Jie. Research of intelligent micro-site selection of wind farm in high altitude mountainous areas based on GIS[J]. Geomatics World, 2018, 16 (1): 130-134.
[14] 仲炜,葛莹,张杰. 基于GIS的高海拔山区风电场智能微观选址研究[J]. 地理信息世界,2018, 16 (1): 130-134.
[15] 高煜坤,李杨,王辉. 浅谈风电项目环评影响评价中风电场选址的论证条件[J]. 资源节约与环保,2014, 32(4): 22-23.
[1] 杨红,王智伟. 多热源集中供热系统水力性能优化方法[J]. 分布式能源, 2022, 7(2): 34-43.
[2] 董霞威, 马长啸, 黄海, 朱振武, 蔡恩雨, 李学峰, 郭正中, 莫纶民, 康宏. 分布式光伏项目国企开发模式及风险研究[J]. 分布式能源, 2021, 6(6): 24-30.
[3] 曹蕃, 郭婷婷, 殷爱鸣, 陈坤洋, 金绪良, 张丽, 杨钧晗. 风光氢混合发电系统设计与能量管理策略研究进展[J]. 分布式能源, 2021, 6(4): 1-14.
[4] 张桂红, 张雨津, 刘飞, 傅旭. 多能互补系统化学储能电站建设需求分析[J]. 分布式能源, 2021, 6(4): 70-76.
[5] 王俊杰,郭霄宇,王含,张谨奕,白宁,孙嘉. 冷热双蓄与热泵耦合的综合能源系统经济效益分析[J]. 分布式能源, 2020, 5(5): 64-70.
[6] 张谨奕, 白宁, 李京浩, 王含, 郭霄宇, 韩雨辰, 张玮. 基于Simulink的热泵储电系统动态仿真[J]. 分布式能源, 2020, 5(3): 15-22.
[7] 李琼慧, 叶小宁, 胡静, 黄碧斌, 王彩霞. 分布式能源规模化发展前景及关键问题[J]. 分布式能源, 2020, 5(2): 1-7.
[8] 臧宝志, 吴长龙, 朱宏光, 魏莘, 高建宏, 吕倩楠. 电价引导下的电动汽车负荷特性[J]. 分布式能源, 2020, 5(1): 44-51.
[9] 宋宏升. 大型办公区分布式多能耦合能源站运行策略优化[J]. 分布式能源, 2020, 5(1): 52-59.
[10] 秦鸣泓,杨胜云,常湧. 基于PSCAD/EMTDC的光伏并网系统建模与仿真[J]. 分布式能源, 2019, 4(4): 10-16.
[11] 郑熠旻. 考虑功率偏差的工业园区光伏与储能联合优化[J]. 分布式能源, 2019, 4(3): 16-20.
[12] 李子申,赵嘉玮,单东雷,刘伟,赵志勇. 燃气分布式能源系统的典型案例分析[J]. 分布式能源, 2019, 4(1): 32-37.
[13] 李斌. 风电场精细化微观选址技术的创新应用[J]. 分布式能源, 2018, 3(5): 59-64.
[14] . 基于粒子群算法的风电系统调峰策略[J]. 分布式能源, 2018, 3(3): 15-21.
[15] 方佳良, 臧兴海, 江岳文. 配电网接入分散式风电的扩容效益研究[J]. 分布式能源, 2018, 3(3): 28-33.